School Solar & PPA/ Decision guide

Published 10 October 2026 / Practical appraisal

From solar proposal to defensible school decision

A worked appraisal, proposal comparison and evidence checklist for school and trust leaders assessing long-term solar agreements.

A credible proposal joins demand, design, price, responsibilities and an achievable approval route. The worked example below is invented for teaching the arithmetic. It is not a school case study, market quote or prediction.

One illustrative school, several possible outcomes

Start with 100,000kWh of year-one solar generation, of which 70,000kWh is consumed onsite. The remaining 30,000kWh is surplus. The school pays 15p/kWh only for onsite energy, avoids 22p/kWh of imported costs, retains no export income and incurs £500 of additional annual costs plus £1,000 at the outset.

Year-one cash-flow bridge: illustrative inputs, consistent tax basis
ComponentCalculationAmount
Avoided import cost70,000kWh × 22p£15,400
PPA electricity payment70,000kWh × 15p£10,500
Gross differenceAvoided cost less PPA payment£4,900
Additional annual school costEntered allowance£500
Year-one operating differenceGross difference less annual cost£4,400
Initial school costTime-zero cash flow, deducted separately£1,000

The 22p input excludes charges that the school still pays. Do not replace it with a whole-bill average unless the avoided components have been checked. Prices and costs use one consistent tax basis; actual VAT recoverability and other tax treatment need to be resolved in the school’s own appraisal.

Why the contract’s purchase obligation matters

If the school must pay 15p for every generated kilowatt-hour, the year-one PPA payment becomes £15,000. With the same onsite use, retained costs and no export income, the operating difference becomes -£100. If onsite consumption instead falls to 50% while payment remains for onsite energy only, the operating difference becomes £3,000. These are different contractual and demand assumptions, not arguments that every PPA has those terms.

Look across the term

The following three paths assume 0.5% annual generation decline, constant onsite share, 2% annual PPA escalation, fixed £500 annual school costs and a 3.5% discount rate. All are illustrative nominal assumptions, not official recommended values. Cash flows are year-end; the initial £1,000 is at time zero. Export prices, if entered in the interactive tool, remain constant.

20-year illustrative comparison, including initial cost
Avoidable grid-price pathYear-one operating differenceFinal-year operating differenceUndiscounted totalDiscounted differencePPA unit price above grid
Falling grid prices£4,400-£6,558-£29,043-£11,628Year 9
Level grid prices£4,400-£406£40,240£32,374Not within term
Rising grid prices£4,400£10,144£139,235£93,831Not within term

The discounted difference is not a complete investment valuation. Add actual roof-work timing, downtime, changing demand, variable fees, tax effects, financing and end-of-term costs. A favourable total does not remove annual affordability or contractual risk. A unit-price crossing year alone does not capture payment for surplus energy.

Four kinds of price evidence

Use each price for the question it can answer
EvidenceWhat it tells youWhat it cannot establish
Observed wholesale indexDated short-term market conditions; £/MWh ÷ 10 converts to p/kWh.A school’s delivered bill, solar capture price or future tariff.
Forward market quotationA price for a defined future delivery period, product and quote time.A guaranteed realised price or a school-specific supply offer.
School supply/PPA quotationTerms offered to the school, with profile, charges, validity and tax basis.Savings without usable generation, retained-cost and full-term analysis.
Illustrative scenarioSensitivity to explicitly chosen price paths.A forecast, probability or claim about the market’s expected direction.

The electricity desk has a dated Elexon archive and refresh path. A licensed forward-price feed is not connected. We will not populate a forward curve from historical observations or present the calculator’s 25p grid / 15p PPA defaults as available offers.

When forward information is supplied, record quotation time and timezone, delivery dates, baseload or peak profile, currency/unit, settlement versus bid/offer, source, usage rights and stale-data policy. A baseload strip supplies every hour; a school’s load and a rooftop’s solar output do not. Procurement margins, hedging and non-commodity costs need a separate bridge to the school quote.

The weekday 08:00–16:00 chart includes holidays. To assess solar’s value, match generation and school demand interval by interval: onsite use equals the smaller of the two, surplus is accounted for separately, and financial treatment follows the actual contract. Avoid applying a single national wholesale average to every generated kilowatt-hour.

ICE’s UK baseload product definition · Elexon’s observed Market Index · Ofgem’s business-bill context

Compare the whole proposal

Use the same site, demand record, generation method and comparison period for every proposal. Ask suppliers to identify assumptions and exclusions rather than filling unknowns with optimistic numbers. The worksheet is a record of questions, not a substitute for technical, procurement or legal advice.

Proposal scrutiny: evidence to obtain before commitment
AreaEvidence requestQuestion to resolve
Demand and designA year of half-hourly demand, holiday/lettings calendar, proposed generation profile and the effect of planned efficiency works.A large roof or annual electricity total alone cannot establish usable solar.
Roof and electrical worksCondition and structural surveys, remaining roof life, asbestos assessment where relevant, electrical capacity, access and connection responsibilities.Who pays for roof repairs, isolation, removal and reinstatement during the term?
Consents and procurementLandowner/responsible-body authority, applicable school-land approvals, planning and connection route, and a documented procurement/value-for-money assessment.A registration or expression of interest is not permission to sign.
Price and purchased energyStarting tariff, indexation formula/caps, invoice basis and whether payment covers onsite use or all generated energy.Who pays for surplus generation and who receives export revenue?
Performance and maintenanceExpected yield, monitoring access, fault response, maintenance scope, warranties, exclusions and any enforceable performance commitments.A forecast yield is not a contractual guarantee.
School’s retained costsMetering, network/supply charges, insurance changes, surveys, professional fees, tax treatment and any annual service payments.Only demonstrably avoidable import costs belong in the savings input.
Change and exitSchool closure/expansion, academy transfer, counterparty failure, assignment, termination payments and funder rights.Ask advisers to examine the actual drafted clauses and adverse circumstances.
End of termOwnership transfer or removal, roof reinstatement, residual value and treatment of equipment reaching end of life.Do not assume ownership transfers free of cost.
Battery and resilienceSeparate storage cost, replacement, losses, control and income allocation; explicit backup capability if proposed.Solar generation alone does not establish power-cut resilience.
Evidence and educational useMetered generation/import/export, dated baseline, tariff reconciliation, pupil activities and a named monitoring owner.Evaluate educational benefits separately from cash savings; do not monetise them without evidence.
Download blank supplier A / B / C comparison worksheet

A board paper that survives the adverse case

Establish the baseline

Name the responsible body and project sponsor. Attach dated bills, interval data, surveys, roof programme, generation design and an explanation of which costs are avoided. List missing evidence with an owner.

Show the alternative

Compare the PPA with doing nothing and feasible alternatives, including demand reduction and a funded/capital route where available. Grant-funded programme returns do not establish the return from a school’s proposed PPA.

Explain the downside

Show lower onsite use, cheaper imported power, reduced yield, additional school costs and the actual obligations for surplus generation. Discuss cash flow, termination and roof works across the agreement.

Define the decision

Separate permission to investigate from authority to commit. Record reviewer conclusions, procurement/consent status, unresolved conditions and when the board will revisit the proposal.

After installation, assign an operating owner for meter reconciliation, fault reporting, performance review and educational use. A saving is stronger evidence when another reviewer can reproduce it from generation, imports, exports, invoices and the documented baseline.

Evidence update register

Supplement published 10 October 2026; original features remain dated 9 October
Evidence itemThis reviewNext evidence needed
Programme countsSeparated funded installations, planned expansion and private-finance pilot.A later official school-by-school completion record.
Case studiesAdded published project tables, participant accounts and delivery lessons.Matched bills and metered results before claiming audited solar-only savings.
PricingRetained observed data / forward quotes / school quotes / scenarios distinction.Licensed timestamped forward source and genuine school quotations.
AppraisalAligned default inputs; added upfront cost, export rights and purchase obligation to stress test.School-specific technical and contractual inputs with consistent tax treatment.
DfE templatePublished guidance checked; final approved templates still awaited on that source.Official publication and confirmation of resumed approvals.

Evidence reviewed 2026-10-10. Original interviews and unpublished partner claims have not been invented. Public-source interpretation is School Connection’s assessment. Any future commercial participation must remain separately disclosed.

Examine the participating-school evidenceReturn to the programme

From interest to operation

Understand the delivery stages, responsibilities and first-year evidence.

From interest to switch-on, and the first year afterwards

Energy pressure and school budgets

Dated spending evidence, participating school leaders’ experiences and practical choices across efficiency, procurement and solar.

School energy bills: the pressure, the choices and what leaders can control